T7041333 : ADA Accessibility at Broadway Junction on the Fulton Street Line - Design Only

Budget
Submission
As Of

Description


Change Narrative
Plan Year
2015
Allocation
Plan Year
2016
Allocation
Plan Year
2017
Allocation
Plan Year
2018
Allocation
Plan Year
2019
Allocation

Out Years
Allocation

Total
Allocation
 
 
2018 Apr. ADA: Broadway Junction FUL DES  Initial funding was provided for design from the "ADA Enhancements at Various Locations" project; additional funding for subsequent phases of design and construction will be transferred accordingly.         $313   $313
 
2019 Sept ADA: Broadway Junction FUL DES           $313   $313
 
2024 Dec. ADA: Broadway Junction FUL DES           $313   $313
 
Current ADA Accessibility at Broadway Junction on the Fulton Street Line - Design Only  Schedule updated to reflect current work plan. Budget change due to financial closeout activities.         $303 $183 $486