T7041404 : Reconstruction of Times Square Shuttle - Phase 3

Budget
Submission
As Of


Description


Change Narrative
Plan Year
2015
Allocation
Plan Year
2016
Allocation
Plan Year
2017
Allocation
Plan Year
2018
Allocation
Plan Year
2019
Allocation

Out Years
Allocation

Total
Allocation
 
 
2014 Sept Reconstruction: Times Sq Complex, Ph3 - Shuttle   $1,065   $28,935       $30,000
 
2017 Aug. Reconstruction: Times Sq Complex, Ph3 - Shuttle   $1,065   $28,935       $30,000
 
2018 Apr. Reconstruction: Times Sq Complex, Ph3 - Shuttle  The timing of approval of the 2015-2019 Capital Program required the schedule of this project to be adjusted. $1,116   $864 $27,376     $29,356
 
Current Reconstruction of Times Square Shuttle - Phase 3   $1,116   $2,264 $19,953 $6,022   $29,355